Vengalam-Pooladikkunnu bypass will open by January-DC

District Collector N.Prasanth has said that Vengalam-Pooladikkunnu bypass will open for transportation by January third week.
He was evaluating the progress of road construction.
The work has been moving quickly as per the special direction by the Chief Minister.
The collector appreciated the public works department officials and Uralunkal Labour Contractor’s Co-operative Society workers.
The completion of the road earlier than the prescribed date is history-he said.
As per the agreement,the contractors were given 28 months to complete the project.
When Chief Minister visited the work site few days back,had asked them to complete within 18 months.
However,the work is completing within 15 months.